Big Milestone 5/26/26

The HydraVault design and construction team — Syska Hennessy, Power Construction, and HydraVault — traveled to Sheboygan, WI, to visitRehlko formerly Kohler and witness run testing of the new generators.

No surprise: the generators passed with flying colors.

Even better, Rehlko has already completed four of the eight 2.5 MW generators planned for installation at HydraVault — ahead of schedule.

Great progress from a great team!