Construction Update 9/14/26

Great construction progress at HydraVault to share.

ComEd, the electrical utility provider for HydraVault, today made great progress towards completing the 20 MW line extension into the HydraVault data center site.

See attached a few of the photos from today:

  • ComEd’s contractor installing the 20 MW electrical feeder vault adjacent to the HydraVault property.
  • Underground electrical conduit for the 20 MW line extending directly into the HydraVault site.

I’m told that tomorrow, the ComEd contractor plans to return to run more conduit through the underground electrical vault and into our site.

More pictures to come.